New Location Update

21 10 2008

It’s been a busy day here at the new location.  We have some volunteers coming out every day right now for about an hour doing drywall for us.  They are also going to help us with some of our flooring.  Our mud and tape guys started today and already have 2 coats done in the welcome center and started in the worship center.  Toilets and urinals have been ordered and are ready to install.  We have someone ready to paint everything starting November 1st.  Electricians are moving right along on target.  Below are the latest pictures.  Exciting stuff.  November 23rd is still our goal.  Please continue to pray with us that the Lord grants us favor in this process.